Project Name :
The Procurement, Supply, Installation, Hook-up, Pre-Commissioning & Assistance in Commissioning & Start-up of the 33KV Overhead Transmission Line
Client : TOTAL E&P Yemen
Location : Kharir, Yemen
Awarded Date : April, 2011
Completion Date : October, 2013
Project Scope : Engineering, procurement & installation of poles with all necessary isolators, switches and terminations, including installation of Steel Lattice Towers close to the Kharir Power Plant Location and installation of overhead transmission line also termination of overhead line, and fiber optic cable including installation of earth electrodes for each pole and earthing of pole and pro-commissioning activities for all works.