Client : Ministry of Equipment and Transport

Location : Corridor Arta - Dikhil Road, Republic of Djibouti

Awarded Date : March, 2004

Completion Date : December, 2004


Project Scope : Rehabilitation of International Corridor Arta - Dikhil Road, for a length of approximately 90 km.

February 2004, this project was awarded to HAWK International.

The scope of work included earthworks, repair of drainage installations, rehabilitation by scarification of the existing road, subbase, crushed stone base-course, asphaltic wearing course, double bituminous surface dressing and road furniture.

Work in particular included foundation preparation, 15cm crushed stone base (wherever required), prime coat and asphalt concrete wearing course and double surface dressing. Also, Irish crossing and box culverts and other drainage and protection works for a length of approximately 90 kms.